Treatment Plant Odor Control Construction Updates

Treatment Plant Odor Control Project Update - Aug. 16

During the next few weeks, construction crews will continue work on the biofilter foundation. Forms and rebar will be installed next week, and concrete is expected to be delivered on Monday, Aug. 26.

In addition to the odor control project, a separate project to connect a new sewer line into the treatment plant is underway. Contractors working on this project are digging and chipping through bedrock near the plant. The project is expected to last three more weeks. Residents living near the treatment plant may hear noises resulting from this excavation during construction hours.

Treatment Plant Odor Control Project Update - Aug. 2

For the next few weeks, construction crews will be working on electrical utilities and the biofilter foundation. This includes:

  • Connection of main electrical lines from a junction box to a transformer.
  • Layout and excavation of footings for biofilter.
  • Subgrade preparations for footings.
  • Installation pf forms and rebar for footings and footing walls.
  • Pouring concrete into forms.

Treatment Plant Odor Control Project Update - July 19

During the next few weeks, construction crews at the wastewater treatment plant are working on site preparation and underground utilities. Work includes:
  • Mobilizing equipment 
  • Staging materials 
  • Sedimentation and erosion control
  • Moving an existing underground main electrical utility feeder line
Earlier this week, a public engagement meeting was held to talk with residents about the project. Thanks to everyone who visited!