Main Street Turn Lane

Main StreetTransportation Bond-Funded Project

Adding new right turn lane on Main Street (from near Earp Street to Holly Springs Road), giving turning traffic a place to stack so northbound through-traffic on Main Street can keep moving.

Location:

Northbound Main Street, near Earp Street to Holly Springs Road

Completed

  • Survey work
  • Roadway design
  • Public meeting held (October 2019)
  • Tree study by arborist

Under Way

  • Duke Energy utility relocation design

Project Status Bar graphic

Estimated construction start:

2021

Public engagement:

June 4, 2019 open house - See survey limits map displayed at the meeting.

Oct. 24, 2019 public meeting - See proposed project design displayed at the meeting.

Contact:

Holly Springs Engineering: (919) 557-3938

Web page last updated:

September 2020