Avent Ferry Sewer Force Main Upgrade

Project description:

Replacing about 8,500 linear feet of existing 8-inch sewer line with larger 18-inch line to provide additional system capacity and improve efficiency of nearby sewer pump station.

Avent Ferry Force Main

Location:

Along the existing sewer force main that travels near the Braxton Village and Holly Glen neighborhoods and through Duke Energy property to the wastewater treatment plant.

Status:

Under construction


Estimated construction start: 

January 2021

Public engagement:

A public engagement meeting was held April 22, 2020. Click here for information shared at the meeting.

Attended Braxton Village homeowners association meeting in February 2020.

Additional information:

Construction noises may be heard during work hours, 7 a.m.-6 p.m., Monday through Friday. Some work could occur on Saturdays between 8 a.m. and 6 p.m. if the project falls behind schedule due to weather delays or other factors beyond the contractor’s control. Work on any section of a sewer easement that falls within a residential property is limited to 8 a.m.-5 p.m., Monday through Friday. Construction is expected to be completed in late fall. 

Click here to view a map of the project area.

  1. Dirk Siebenbrodt

    Project Engineer
    Phone: (919) 557-3931

  1. David Summers

    Development Construction Coordinator
    Phone: (919) 557-2910

Web page last updated:

Dec. 31, 2020