New Hill Road Sidewalk

Project description:

Construction of approximately 800 linear feet of a new 5-foot wide sidewalk, located on the north side of New Hill Road, will create a pedestrian connection between the existing Holly Springs Towne Center shopping center to the east and proposed and existing sidewalks to the west.


Status:

  Conceptual 
>Design
>Right-of-Way Acquisition
  Under Construction
  Complete

New Hill Road Sidewalk

Schedule:

Design CompleteSpring 2018
Right-of-Way AcquisitionSummer 2018
BiddingFall 2018
ConstructionFall 2018
ClosuresN/A

Project information:


16-005 Plans/Exhibits Click here to view plans.

Contact information


Engineering


For more information about transportation (roads, intersection improvements, sidewalks), water, sewer and stormwater, contact Engineering.
email | (919) 557-3939

Planning & Zoning


For more information about land use, building setbacks, parking, landscaping, architecture and design, contact Planning & Zoning.
email | (919) 557-3908