Town Hall Commons Utilities and Infrastructure Improvements

Project description:

The town is adding parking and a regional stormwater control measure, extending Rogers Road, and updating the water and sewer lines to support the addition of 100,000 square feet of restaurant, retail and office space in downtown Holly Springs.

Status:

  Conceptual 
  Design
  Right-of-Way Acquisition 
>Under Construction
  Complete

Town Hall Commons

Schedule:

Design Complete2017
Public Meeting2017
Right-of-Way AcquisitionN/A
BiddingFebruary 2018
ConstructionSpring 2018 - Spring 2019
ClosuresDuring construction, parts of Avent Ferry Road and Ballentine Street will be temporarily closed, as well as parts of Raleigh Street and Rogers Street. 

Businesses and parking lots near Town Hall remain open.


Contact information


Engineering


For more information about transportation (roads, intersection improvements, sidewalks), water, sewer and stormwater, contact Engineering.
email | (919) 557-3939

Planning & Zoning


For more information about land use, building setbacks, parking, landscaping, architecture and design, contact Planning & Zoning.
email | (919) 557-3908