Utley Creek Greenway

Description

The Utley Creek Greenway project will add about 4,740 linear feet of greenway to provide a connection between west and east Holly Springs via an existing pedestrian tunnel under NC 55 Bypass. Once complete, the greenway will travel from W. Ballentine Street near the Oaks of Avent Acres club house, along an existing greenway, through the pedestrian tunnel, and then on to Avent Ferry Road. The work is funded in part with an 80/20 match (up to $725,000) from the Congestion Mitigation and Air Quality Improvement Program fund. Once completed, the greenway will provide a pedestrian and bicycle connection totaling about 6,460 linear feet.

Schedule

December 2017-June 2019: Design, permitting, right-of-way acquisition, bidding
June-December 2019: Construction 